Nicosia-Iskele Road Maintenance and Repair Work started

As of 2nd November, maintenance and repair works started on the part of the Nicosia-İskele road between the Ercan Junction and İskele.

As a result of the work to be done in stages, damaged parts and crash barriers on the road in question will be repaired.

The work is expected to last for a maximum of 2 months, depending on weather conditions, and within the scope of the work 5,700  tons of asphalt will be laid in an area of approximately 41,000 m2, thermoplastic paint lines will also be drawn. Maintenance and repair of the road will cost 2.4 million TL.

Source: Ministry of Public Works and Transportation